| Contract ID | B14-3349 | Name | County Road 134 Bridge over Union Pacific Railroad |
| 0.573 Miles of Construction of a Bridge and Approaches on County Road 134 over Union Pacific Railroad. | |||
| Diary Date | 04/30/2006 | Diary Author | Jerry Dell | Diary Status | Submitted For Payment | Status Date | 04/30/2006 |
| Contract Time | |||||||
| Type | Number | Description | Time Charge | ||||
| Contract | 1 | Contract Time | 16.00 DY | ||||
| Intermediate | 2 | Lane Closure | 3.00 HR | ||||
| Daily Work Report by Jack Dane | |||||
| Report Date | 04/30/2006 | Diary Status | Submitted For Approval | Status Date | 04/30/2006 |
| Temperature | High: 78F Low: 56F | Conditions | AM: cloudy PM: clear | ||
| Contractor Supervisors | ||
| Contractor | Supervisor | Hrs Worked |
| Gibson Construction, Inc. | Jeff Dall | 6.00 |
| Contractor Workers | |||
| Contractor | Type | Number of Persons | Hours Worked |
| Gibson Construction, Inc. | Driver | 2 | 6.00 |
| Contractor Equipment | ||||
| Contractor | Equipment | Number of Pieces | Number Used | Hours Used |
| Gibson Construction, Inc. | Cement Truck | 2 | 2 | 6.00 |
| Agency Staff Work | |||||||
| Staff Member | Employer Type | Work Type | Regular Hours | OT Hours | Vehicle ID | Starting Mileage | Ending Mileage |
| Jack Dane | Agency | Work | 8.00 | 0.00 | DOT-1604 | 87,323.9 | 87,348.2 |
| Daily Work Report by Jake Dock | |||||
| Report Date | 04/30/2006 | Diary Status | Submitted For Approval | Status Date | 04/30/2006 |
| Temperature | High: 78F Low: 56F | Conditions | AM: cloudy PM: clear | ||
| Contractor Supervisors | ||
| Contractor | Supervisor | Hrs Worked |
| Gibson Construction, Inc. | Jeff Dall | 5.00 |
| Contractor Workers | |||
| Contractor | Type | Number of Persons | Hours Worked |
| Gibson Construction, Inc. | Driver | 1 | 5.00 |
| Contractor Equipment | ||||
| Contractor | Equipment | Number of Pieces | Number Used | Hours Used |
| Gibson Construction, Inc. | Cement Truck | 1 | 1 | 5.00 |
| Agency Staff Work | |||||||
| Staff Member | Employer Type | Work Type | Regular Hours | OT Hours | Vehicle ID | Starting Mileage | Ending Mileage |
| Jake Dock | Agency | Work | 8.00 | 0.00 | DOT-2395 | 32,582.0 | 32,605.1 |
| Work Item Progress | |||||
| Project / Group / Seq # | Item | Location | Units | Installed Quantity | |
| F23B-14003 / 1 / 000090 | 500-3101 - Class A Concrete | Station 12+3.000 | CY | 1.000 | |
| F23B-14003 / 1 / 000155 | 643-0104 - Field Fence Barbed Wire, 4 Strands | Station 12+7.000 | LF | 147.000 | |
| F23B-14003 / 2 / 000190 | 500-3101 - Class A Concrete | Station 1+2.000 | CY | 24.000 | |
| F23B-14003 / 2 / 000190 | 500-3101 - Class A Concrete | Station 1+7.000 | CY | 16.000 | |
| F23B-14003 / 2 / 000210 | 520-1316 - Piling in Place, Metal Shell, 16in OD | Station 1+17.000 | LF | 87.000 | |
| F23B-14003 / 2 / 000210 | 520-1316 - Piling in Place, Metal Shell, 16in OD | Station 1+19.000 | LF | 22.000 | |